Renovation

EPC 02 - Oak Street Chiller Plant

Started: 06/01/2012

Completed: 04/09/2013

This project gives the university greater flexibility in choosing a fuel source for cooling generation and an estimated energy savings of $1.2M annually.

Oak Street Chiller Plant – EPC Project 02 (U11080)

This $10.7M project included the installation of two, new electric, high-efficiency, large-tonnage chillers; a cooling tower; a refrigerant storage unit; and a 10mVa transformer. It gives the university greater flexibility in choosing a fuel source for cooling generation and an estimated energy savings of $1.2M annually.

Notable energy conservation measures

  • Water-cooled Chillers
  • Refrigerant Storage
  • Cooling Towers